Hydrocracking Unit – TX

50K BPSD Hydrocracking Unit (HCU) – Shell Companies seem to dislike the term ‘turnaround consulting’ because it represents failure. The truth is that turnaround consulting represents success at realizing the company is going in the wrong direction. The only time the company fails is when it is not possible to do a turnaround anymore. We […]
Renewable Fuels – LA

10K BPSD Green Diesel Hydrotreater Joint venture execution UOP licensed technology Green Diesel Hydrotreater, Pre-Treating Facility, Tankage, Rail Off-Loading and Offsites Fast-paced schedule – detailed engineering and design schedule of only 12 months Overall schedule – 22 months Complex rail off-loading scheme: frozen tallow and grease from all parts of the country arriving at varying […]
Hydrocracking Unit – LA

50K BPSD Hydrocracking Unit SC Shell licensed technology Overall Construction Management Responsibilities Direct hire Mechanical construction execution Developed scheme to offload reactors that shortened construction schedule Over 250,000 detailed design and engineering man-hours 1,200,000 construction man-hours Total RIG man-hours: approximately 1,450,000 Includes HCU, Light Ends Unit (LEU), Sour Water Stripper (SWS), Amine Treating Unit (ATU) […]
Crude Unit Revamp – TX

250k BPSD Crude Unit Revamp – Canadian Crude Revamp an existing crude unit to run Canadian crude New pre-flash section Over 150 tie-ins with zero errors or omissions Total RIG man-hours: 150,000
Kerosene Hydrotreater – OH

20K BPSD Kerosene Hydrotreater Axens technology Conventional stick built design Aggressive 13 month engineering-to-commissioning schedule Total RIG man-hours: 50,000
Railcar Projects

Railcar Unloading Facility designed to receive feed stock via railcar RDS responsible for FEED and Detail Design RCI responsible for Construction Management Railcar Crude Unloading Civil, ME, Process, E/I and Pipe designers RDS responsible for FEED and Detail Design Crude by Rail Facility designed to receive feedstock via railcar RDS responsible for FEED and Detail […]
Modularlization

50K BPSD Hydrocracking Unit (HCU) – Shell Project 12K BPD Oil Refinery Gasoline Hydrotreater Duel Amine Treating Units Amine Filtration Units Diesel Hydrotreater Fluorocarbon Unit Sulfur Recovery Unit Tail Gas Treating Unit Sat Gas Unit High Pressure Test Module Number of Modules 82 54 54 12 56 130 31 20 53 55 Project & Number […]