Renewable Fuels – LA
10K BPSD Green Diesel Hydrotreater

- Joint venture execution
- UOP licensed technology
- Green Diesel Hydrotreater, Pre-Treating Facility, Tankage, Rail Off-Loading and Offsites
- Fast-paced schedule - detailed engineering and design schedule of only 12 months
- Overall schedule - 22 months
- Complex rail off-loading scheme: frozen tallow and grease from all parts of the country arriving at varying temperatures
- Purchased 420 pieces of tagged equipment and instruments
- 12 storage tanks
- Responsible for shop inspection and expediting
- Overall construction management
- Mechanical, electrical and instrumentation by joint venture partner
Total RDS Engineering and Design man-hours: 200,000
Civil construction responsibilities:
- 4,000 timber piles
- 15,000 cubic yards of concrete
- 16,000 linear feet of underground pipe